Sorry for not making it clear since Im too rushing yesterday
As we know Budgeted Quantity = Original duration*units per day right? but the problem is all my UPT (units per day) remain to 1. Is not suppose to be, becuase it would calculate automatically once we drop BQ and OD status.
What I did yesterday, I convert it to P3 version then export it to excel direct do correction.
Done perfectly, but I didnt find it at P6 software. Could u tell how to do this at p6 via excel spreadsheet?
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Izam,
Okey. You mean Export P6 to Excel sheet. You can even do this in P6 itself using global.
So, what exactly you need to export and modify it in Excel? The Units/Time, Budgeted Units or Duration?
I think the reason why the UPT remain to 1 it is because, the duration type is "Fixed Units/Time". Try to change it to "Fixed Duration & Units".
Now if you are trying to update your schedule, the UPT will change depending on the "Remaining Duration & Units".
Hope this helps.
Regards,
Arnold
Hi Arnold,
Sorry for not making it clear since Im too rushing yesterday
As we know Budgeted Quantity = Original duration*units per day right? but the problem is all my UPT (units per day) remain to 1. Is not suppose to be, becuase it would calculate automatically once we drop BQ and OD status.
What I did yesterday, I convert it to P3 version then export it to excel direct do correction.
Done perfectly, but I didnt find it at P6 software. Could u tell how to do this at p6 via excel spreadsheet?
Hi Izam,
Can you cite an example, a little bit clearer.
Regards,
Arnold
To make it clear, its loading 5 mhrs only per week....