Cost Loaded Schedule Import Error

3 replies [Last post]
zahid shaikh
User offline. Last seen 6 years 33 weeks ago. Offline
Joined: 24 Aug 2016
Posts: 35

When I Import my Cost Loaded Schedule from One Computer to another the Cost from Project Reduces..

Cost for Many activities goes missing.

But the main computer in which the Cost Loading was done, If I import it again on the same computer Cost comes correct

Replies

Zoltan Palffy
User offline. Last seen 17 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

that should work 

zahid shaikh
User offline. Last seen 6 years 33 weeks ago. Offline
Joined: 24 Aug 2016
Posts: 35

Budgeted Total cost goes missing.

 

I will try using the add new resource setting.

Zoltan Palffy
User offline. Last seen 17 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

which costs are we talking about budgeted, actual, actual at completion which one ?

also check your filter make sure that it is set to ALL

also go to Projects directory make sure you project is highlighted 

got to the calculations tab 

on the right under the Resource Assignments make sure that Add actual to remaining is checked.

also during the import process make sure that in the Update Project Options that select modify

under the Data Type Activity: make sure that the action for activity resource assignment is set to insert new

under the Data Type Global: make sure that the action item under resources is set to insert new