Updating via Importing Data from Another Project
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi R Jones,
First of all, welcome to Planning Planet.
Well, it is not very clear for me however, let me answer your question. But first make a backup to your project.
In order to update your Baseline Resource Quantities, go to Project --> Maintain Baselines and select the Baseline you wanted to update.
Select the "Update" button remove all the checks except for "Update exisitng activities already in the baseline" & "Ignore Last Update Date". In Specify the activities to include: select the "All activities" or filter the folowing activities you want to change.
Then select the "Update Options" radio button, under the "When updating resource assignment data, include:
Mark the checkbox next to "Update existing resource and role assignments" & "Budgeted units and cost" & unselect the rest of the checkbox then ok.
Then select "Update".
You can easily perform this exercise in excel sheet.
HTH.
Regards,
Arnold