Updating via Importing Data from Another Project

Member for

18 years 6 months

Hi R Jones,



First of all, welcome to Planning Planet.



Well, it is not very clear for me however, let me answer your question. But first make a backup to your project.



In order to update your Baseline Resource Quantities, go to Project --> Maintain Baselines and select the Baseline you wanted to update.



Select the "Update" button remove all the checks except for "Update exisitng activities already in the baseline" & "Ignore Last Update Date". In Specify the activities to include: select the "All activities" or filter the folowing activities you want to change.



Then select the "Update Options" radio button, under the "When updating resource assignment data, include:

Mark the checkbox next to "Update existing resource and role assignments" & "Budgeted units and cost" & unselect the rest of the checkbox then ok.



Then select "Update".



You can easily perform this exercise in excel sheet.



HTH.



Regards,



Arnold