Resource Dependent Planning

O
Oliver Melling 👤 Member for 19 years 2 months

The problem was that i didnt have the Drive Activity Dates by Defaults box ticked at project level.



This meant that although the activities were set to resource dependent, the start/finish dates were not driven by the availability of the resource, but followed the activity calendar instead.



I would be interested to know a scenario that would require a resource driven plan not to be driven by the resources availability.



i.e. when would you not want the Drive Activity Dates by Defaults box ticked?