The problem was that i didnt have the Drive Activity Dates by Defaults box ticked at project level.
This meant that although the activities were set to resource dependent, the start/finish dates were not driven by the availability of the resource, but followed the activity calendar instead.
I would be interested to know a scenario that would require a resource driven plan not to be driven by the resources availability.
i.e. when would you not want the Drive Activity Dates by Defaults box ticked?
He has 3 days as the activity is not started.
How many units of work has your primary resource got to complete?