Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Dependant

1 reply [Last post]
Michael Petzer
User offline. Last seen 4 years 22 weeks ago. Offline
Joined: 29 Apr 2021
Posts: 5
Groups: None

Hi all,

When setting up  'resource dependant' activity with a duration of 5 days, then assigning 5 resources to the activity with a shared resource calendar of 4h/d (0800-1200).

Can one still get the activities start, finish & duration to not change as the below is doing?

7731
xxxx.jpg

Replies

Zoltan Palffy
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

no hence the name RESOURCE DEPENDENT. If you want to do this change the activity type to task dependent.

if an activity has been assigned as a resource dependent type of task then the duration will be based on availability for that resource to work on that activity and it will use the RESOURCES CALENDAR NOT the activity calendar.

Try to make the resource calendar as same as the activity calendar and it might do what you want.