Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Status in the Resource Assignments View

5 replies [Last post]
Mark Porter
User offline. Last seen 46 weeks 4 days ago. Offline
Joined: 8 Aug 2007
Posts: 55
Groups: None
Does anyone out there know of a real easy way of determining the activity status of a particular activity when viewing the activity via the resource assignments view?
The best that I can come up with is either a very convoluted filter or using a global change in the activities view to apply a code which I am then able to access in the resource assignments view, however this then becomes static data which requires the re-running of the global change prior to viewing this data.
Mark

Replies

Arnold Puy
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Thanks Dang..I will try..

Regards
Arnold Puy
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi L. Dang,

Great!! How did you paste the image/picture?

Regards,

Arnold
Arnold Puy
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mark,

YES, I think this is the only way we can do.

Arnold
Mark Porter
User offline. Last seen 46 weeks 4 days ago. Offline
Joined: 8 Aug 2007
Posts: 55
Groups: None
Hi Arnold,

I want this functionality in the resource assignments view, not the activity view. Currently I have to either create a filter or run a global change as described earlier
Cheers
Mark
Arnold Puy
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mark,

You can view your activity status even without viewing the resource assignments. In Activity Window, you can display Activity Status in your column for each activity, Not Started, In Progress & Completed. Is this what you mean?

Arnold