Decimals in Total Float - P6 - why?

T
Terry Barber 👤 Member for 18 years 11 months

1 of your activity’s is starting or finishing at ???.10 You need to find it and i assume that you have a few activity’s that have this + 000’10 time period. You need to find the top activity that has this time period and when corrected it will cascade down through your programme and correct them all.

C
Christopher Nicolas 👤 Member for 20 years 2 months

Paul - none of the durations contain decimal points and the calendar is a standard 10 hour day, 6 day week. I am trying to figure it out??

P
Paul Harris 👤 Member for 25 years 3 months

Have you checked the calendar finish times or activity durations, something is probably not matching.





Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

Featured Partner

Top Posters

Pan
0 posts
Tijo Kurian
11 posts
Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts