Performance % Compl vs. Schedule % Compl

3 replies [Last post]
John Drokovic
User offline. Last seen 5 years 44 weeks ago. Offline
Joined: 9 Oct 2009
Posts: 24
Groups: None
What is the difference between Performance % Complete vs. Schedule % Completete (in P6)?

Replies

Barry Fullarton
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 27 Aug 2008
Posts: 101
Groups: None
Hi

I am wanting to set up a Planned Progress S Curve

How do I do this , I want to take the project and extract the Planned Progress Percentages of the Project from start to end , then I want to measure this as actuals during the Project Period

Who can advise what is the best method of doing this
Anu Tor
User offline. Last seen 13 years 33 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 53
The schedule % complete is calculated by (original duration - remaining duration)/original duration. For performance % complete is calculated by earn value / total value.
Arnold Puy
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi John,


The Performance % Complete is used to compute earned value and may be based on the Activity % Complete, and also specifies what percentage of the activity’s planned worth has been earned so far.


The Schedule % Complete specifies how much of the activity’s baseline duration has been completed so far, and also indicates how much of the activity duration should be currently completed, relative to the baseline.

Regards,

Arnold