Cross-project Interfaces

3 replies [Last post]
Dave Rodwell
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 16 Aug 2001
Posts: 11
I have a number of immature projects that when fully developed will have interfaces to other deliverable dates within the suite. The interface points are likely to be milestones. Thus far I am struggling to achieve a link.

All suggestions will be very welcome.

Replies

Dave Rodwell
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 16 Aug 2001
Posts: 11
Thanks Luca, that’s a good tip, I shall try it once I have established the interfaces.

Regards

Dave
Luca Basile
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
At any time you can also run a report in Primavera Enterprise to show only the interprojects links going out from one project

Luca
Dave Rodwell
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 16 Aug 2001
Posts: 11
So now I can answer my own question.

Simply open the relevant projects, select a source milestone in project 1, select a destination milestone in project 2 and check the assign box.

Very easy.