Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Is P6 Sometimes Ignoring Actuals?

1 reply [Last post]
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Dear All,

I’m not really sure about this but it happened when I’m running a schedule with a certain activity that has an actual start earlier than the Data Date. The bar still goes with the Data Date and hasn’t started on the Actual Date, though the status shows an actual duration and a remaining duration.

Note: there is no % progress, only actual start; scheduled by retained logic

any idea?

Replies

Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
I’m sorry, i’ve seen a very thin line in the actual start and I dragged it and it showed blue bar (which means progress), but I don’t want to see progress, Is it possible?