Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Name Fields Are Sometimes Missing In Printed PDF

3 replies [Last post]
Benjamin Feng
User offline. Last seen 1 year 19 weeks ago. Offline
Joined: 9 Nov 2012
Posts: 19
Groups: None

Some Activity Name values are not seen when printing to PDF when using Enterprise version 18.8

Replies

Benjamin Feng
User offline. Last seen 1 year 19 weeks ago. Offline
Joined: 9 Nov 2012
Posts: 19
Groups: None

haha yes. same issue.

Zoltan Palffy
User offline. Last seen 2 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

have you re-booted the computer ?

Benjamin Feng
User offline. Last seen 1 year 19 weeks ago. Offline
Joined: 9 Nov 2012
Posts: 19
Groups: None

"Yield=On" is already present in the PM.INI file.

But the error still persists.

Zoltan Palffy
User offline. Last seen 2 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

The issue is caused by a missing setting in the PM.ini file.

SOLUTION

Edit the user's PM.ini file to add "Yield=ON" under [Printer Options] and save the file. After the user logs out and back in again, the change will be reflected.

The location of the PM.ini file may be in the default location (ex. C:\Program Files\Oracle\Primavera P6\P6 Professional\PM.ini) or in a user's "home" folder (ex. C:\Users\<User Name>\AppData\Local\Oracle\Primavera P6\P6 Professional\).