Expenses in P5

1 reply [Last post]
Seyed Mohammad ha...
User offline. Last seen 8 years 44 weeks ago. Offline
Joined: 1 Oct 2007
Posts: 15
Dear all friends,
Is there any one could help in data input to Expenses in P5 as I’m a new user of this version;I have got some problem with actual costs and expenses % complete and the relation between the fields in cost tab in expenses view?
Thanks in advance
Hadi Fatemi

Replies

Ahmet Cetin
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 8 Feb 2005
Posts: 84
Groups: None
Hello Seyed,

You can enter the actual costs for expenses in Activities view or Expenses view. In activities view, click on Expenses tab, then right click inside the Expenses tab, then add the actual cost column. Then you can enter actual costs using actual cost column. Or using expenses view, right-click on the expenses view, then select columns... and add actual cost column.

Hope this helps,

Ahmet Cetin