P3e - Resource

1 reply [Last post]
khairul izani othman
User offline. Last seen 13 years 36 weeks ago. Offline
Joined: 21 Oct 2007
Posts: 10
hello...

i got problem here..
How 2 assign differance resource in one task..ex: 1 engineer..5 fitter..10 helper..should i use budgeted unit or actual unit or any others?

Replies

Patricia Le Clainche
User offline. Last seen 9 years 52 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None
If I understand your problem correctly :
On Activity View, show the Bottom Layout, and on "Resource tab", add your resources Ids, and then, you just have to fill the Remaining Units ( = Remaining Labor Units) for each of them.

Best regards.