Primavera basically calculates in hours. The displayed activity summary durations in days and weeks etc are calculated from factors in the User Preferences and therefore not all activity durations in days will display correctly when a project has multiple calendars with different hours per day for each calendar. Only activities where the assigned calendar hours per day matches the User Preferences will display the correct duration in days. P3 did not have this problem but SureTrak and MSP does. Asta has neatly programmed this issue out of PowerProject. Therefore different users will see different durations in days for activities in the same schedule when they have different User Preferences or when your client imports a schedule and has different User Preferences.
There is only one calendar for calculating all durations of Projects in the Projects workspace and WBS Nodes which is the default calendar checked in the Calendar form. Therefore when a project has very different calendars to the database Default Calendar is it unlikely that the durations of the Projects in the Projects workspace and WBS Nodes are likely to correct. It would be better for Primavera to calculate these summary durations based on elapsed durations or start and finish dates over a calendar assigned to a Nroject or WBS Node. The current situation does not allow any level of confidence of project or WBS Node durations.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
I have summaries that show a completely different total duration then what the task sequence should add up to. All calendars are linked correctly, I am assuming it might be the settings mentioned earlier. Like in MS Projects, Tools Options Calendar settings, you can also set the hrs p/d, p/wk and p/mnth, if you change the durations there, it will affect your task and summary durations.
im also not sure (to be honest); it seems that P5/P6 only considers an "8 hr/day work" when counting total durations irregardless of the specific calendar used. ..
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Primavera basically calculates in hours. The displayed activity summary durations in days and weeks etc are calculated from factors in the User Preferences and therefore not all activity durations in days will display correctly when a project has multiple calendars with different hours per day for each calendar. Only activities where the assigned calendar hours per day matches the User Preferences will display the correct duration in days. P3 did not have this problem but SureTrak and MSP does. Asta has neatly programmed this issue out of PowerProject. Therefore different users will see different durations in days for activities in the same schedule when they have different User Preferences or when your client imports a schedule and has different User Preferences.
There is only one calendar for calculating all durations of Projects in the Projects workspace and WBS Nodes which is the default calendar checked in the Calendar form. Therefore when a project has very different calendars to the database Default Calendar is it unlikely that the durations of the Projects in the Projects workspace and WBS Nodes are likely to correct. It would be better for Primavera to calculate these summary durations based on elapsed durations or start and finish dates over a calendar assigned to a Nroject or WBS Node. The current situation does not allow any level of confidence of project or WBS Node durations.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Hello Guys
Doesnt anyone have any comment, you guys are too quiet hey!!!!
I have summaries that show a completely different total duration then what the task sequence should add up to. All calendars are linked correctly, I am assuming it might be the settings mentioned earlier. Like in MS Projects, Tools Options Calendar settings, you can also set the hrs p/d, p/wk and p/mnth, if you change the durations there, it will affect your task and summary durations.
im also not sure (to be honest); it seems that P5/P6 only considers an "8 hr/day work" when counting total durations irregardless of the specific calendar used. ..