Recommended Hours per Time Periods

4 replies [Last post]
Leonard Esber
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 19 Jul 2013
Posts: 16
Groups: None

Hi Colleagues!

Good day.  May I know what are the average/recommended Hours/Month and Hours/Year if I have the following parameters:

a.  8hrs x 7days workweek

         Hours/Day       -  8 hours

         Hours/Week    -  56 hours

         Hours/Month   -  ???

         Hours/Year      -  ???

 

b.  10hrs x 6days workweek

         Hours/Day       -  10 hours

         Hours/Week    -  60 hours

         Hours/Month   -  ???

         Hours/Year      -  ???

 

I'm looking forward for any recommendations.  We know that every each month has different number of days, so I supposed there is something that we can use as averages. 

 

Regards,

Leonard

Replies

Zoltan Palffy
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Here are my suggestions which include 2 weeks vacation

 

a.  8hrs x 7days workweek

         Hours/Day       -  8 hours

         Hours/Week    -  56 hours

         Hours/Month   -  240

         Hours/Year      -  2800

 

b.  10hrs x 6days workweek

         Hours/Day       -  10 hours

         Hours/Week    -  60 hours

         Hours/Month   -  260

         Hours/Year      -  2980

Zoltan Palffy
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Here are my suggestions which include 2 weeks vacation

 

a.  8hrs x 7days workweek

         Hours/Day       -  8 hours

         Hours/Week    -  56 hours

         Hours/Month   -  240

         Hours/Year      -  2800

 

b.  10hrs x 6days workweek

         Hours/Day       -  10 hours

         Hours/Week    -  60 hours

         Hours/Month   -  260

         Hours/Year      -  2980

Zoltan Palffy
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Here are my suggestions which include 2 weeks vacation

 

a.  8hrs x 7days workweek

         Hours/Day       -  8 hours

         Hours/Week    -  56 hours

         Hours/Month   -  240

         Hours/Year      -  2800

 

b.  10hrs x 6days workweek

         Hours/Day       -  10 hours

         Hours/Week    -  60 hours

         Hours/Month   -  260

         Hours/Year      -  2980

Raymund de Laza
User offline. Last seen 19 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Leonard,

Herewith is mu suggestion.

 

a.  8hrs x 7days workweek

         Hours/Day       -  8 hours

         Hours/Week    -  56 hours

         Hours/Month   -  240

         Hours/Year      -  2880

 

b.  10hrs x 6days workweek

         Hours/Day       -  10 hours

         Hours/Week    -  60 hours

         Hours/Month   -  260

         Hours/Year      -  3120

 

Regards,