The 98% Question

1 reply [Last post]
Colin Adam
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 2 Oct 2007
Posts: 10
Why does P5 hang at 98% when opening projects? My PC isn’t doing anything and there’s no network traffic. Spoke to some people from other companies & sites and they experience the same thing. Can’t get a straight answer from anyone. So guess no one really knows ? or do they .....

Replies

Ahmet Cetin
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 8 Feb 2005
Posts: 84
Groups: None
Hello Colin,

If you experience this problem with myPrimavera, the reason is that you are using wrong Java version. If it is Client version then probably you are opening quite big schedule, and it takes time to open it. Otherwise, I never had a problem of opening schedule in client interface. In myPrimavera, yes, because of wrong Java version.

Hope this helps,

Ahmet Cetin

Visit PrimaveraTools.com