Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P5 CANT CHANGE E/S TO ACTUAL DATES

2 replies [Last post]
Donovan Govender
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
Please help urgently, I have imported a MSP project to P5, I have set my schedule and have baselined the schedule and now when I want to progress and put in actual dates it won’t change to new actual start dates

Replies

Donovan Govender
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
Thanks Rony
Rony Roberto
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 10 Oct 2007
Posts: 12
Groups: None
Don,
go to status, click the actual date,then put a value on the peercent complete.




Regards,
rony