Level of effort Progress

3 replies [Last post]
Sander Gorissen
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 30 Aug 2006
Posts: 10
Groups: None
Hi there fellow planners,

I was wondering how the f*ck (sorry ... getting irritated) you could let the progress of a level of effort activity update by progressing underlaying activities.

Many thanks in advance!

Sander

Replies

Sander Gorissen
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 30 Aug 2006
Posts: 10
Groups: None
Thanks Niek,

but that doesn’t work as it is not part of a WBS. I’ve already found the problem. I incorrectly linked the LOE.

thanks again!

Sander
Niek Zonneveld
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Sander,

Why don’t you use a WBS Summary for that?

Cheers,

Niek.
Steven Oliver
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Because thats why LOE (or hammocks) are convenient to use.