Displaying delay of tasks graphically

I
Ijaz Ahmad 👤 Member for 19 years 11 months
P
Patricia Le Clainche 👤 Member for 19 years 1 month



I also agree.

But, what about Technical % complete on a task. Do someone use this data on GANTT chart?



Kindest regards.

Patricia

A
Andrew Dick 👤 Member for 19 years 4 months

Ijaz,

I would use either the original baseline bar and the current bar on the GANTT or see if you can create a special bar by using user_start_date fields filtered on critical activities in conjunction with a global change.



You could populate the start date with the baseline start/finish, and the finish date with the actual/planned start/finish.



Andy