You can either use activity usage profile or resource usage profile
When you use resource usage profile you can select the resource or resources that you want to display in the graph by using the shift/control keys.
otherwise when you use the activity usage profile you can set up the grahp to display either all lab resource or non lab resource in unit or cost in the activity usage profile options.
to open the option you need to right click the mouse and select the options from the menu
Thnks for reply ,i tried the said function and it worked only for indiviual resources..i couldnt get report for cummulative resources for a particular time period.Hope i am clear.
E.g i have A,B,C resources working in project , I want to know total how many required in month.
Member for
22 years 8 monthsRE: Graphic reports
Or one more possibility is using Primavera Earn Value Pack
But it will cost you $.
The only disadvantage of all these is no period performance in P3e ... They (Primavera) said they will introduce the function in the near furture ??
Member for
22 years 8 monthsRE: Graphic reports
You can either use activity usage profile or resource usage profile
When you use resource usage profile you can select the resource or resources that you want to display in the graph by using the shift/control keys.
otherwise when you use the activity usage profile you can set up the grahp to display either all lab resource or non lab resource in unit or cost in the activity usage profile options.
to open the option you need to right click the mouse and select the options from the menu
Hope that helps
Cheers
Alex
Member for
16 years 9 monthsRE: Graphic reports
Thnks for reply ,i tried the said function and it worked only for indiviual resources..i couldnt get report for cummulative resources for a particular time period.Hope i am clear.
E.g i have A,B,C resources working in project , I want to know total how many required in month.
Member for
16 years 9 monthsRE: Graphic reports
thank you
Member for
23 years 8 monthsRE: Graphic reports
Instead of creating the graphic report, the creation is done on display, after that, save the layout as report.
Display the graphic on screen, goto View -> Home, select the option.