Resource Issues

2 replies [Last post]
Minhas Shaikh
User offline. Last seen 13 years 32 weeks ago. Offline
Joined: 30 Mar 2007
Posts: 44
Hi Planners,
In P3e I have assigned resources on given activities. Resource units are labour and material. Most of atvities are linked togather. But One activity creates a huge lag. if I remove resouce from that activity then automatically lag removes. I don’t know where from that lag comes. I need to assign resource on that activity.That activity repeats many times in my schedule.

(2)for checking of resources in resource usage graph I don’t see any unit . It gives zero in total and commulative although activity had been started. or it gives after finishing of activity.

If any body know the solution please reply.

Minhas

Replies

Khuong Do
User offline. Last seen 17 years 3 weeks ago. Offline
Joined: 1 Sep 2006
Posts: 38
Groups: None
Hi Minhas

For second query, the reason you can not see resource graph is unit conflict between labour(hour) and material(e.g feet long)
If a diagram have 2 kind of resource,which have different unit measure, it can not be drawn.

Thanks
Khuong
Dieter Wambach
User offline. Last seen 7 years 23 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Minhas

It seems that your activities are resource driven - activity type: resource dependent and the associated calendar has some holidays or in the master data under "Units & Prices" the maximum units are set to 0.

Regards
Dieter