Resource Issues

K
Khuong Do 👤 Member for 19 years 10 months

Hi Minhas



For second query, the reason you can not see resource graph is unit conflict between labour(hour) and material(e.g feet long)

If a diagram have 2 kind of resource,which have different unit measure, it can not be drawn.



Thanks

Khuong

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Minhas



It seems that your activities are resource driven - activity type: resource dependent and the associated calendar has some holidays or in the master data under "Units & Prices" the maximum units are set to 0.



Regards

Dieter

Forum Sponsor

Top Posters

James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts