Constriant

1 reply [Last post]
Minhas Shaikh
User offline. Last seen 13 years 27 weeks ago. Offline
Joined: 30 Mar 2007
Posts: 44
Hi ,
How can I show constriant date on start or finish. My last actvitiy is going to finish on 5 Dec, 07. But we have to show 29th Nov 07 because its constraint. Can we show 29th November through constraint on start and finish columns instead of constraint column.
Can I fixed 29th November and get backward float.
Thanks
Minhas

Replies

Santosh Bhat
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 15 Apr 2005
Posts: 381
Why not link in a finish milestone at the end of your activities and use a Finish On or Before constraint on that milestone? This is the usual manner of representing compeltion dates.