Progressing without Updating

3 replies [Last post]
Matthew Lovkis
User offline. Last seen 16 years 44 weeks ago. Offline
Joined: 26 Nov 2006
Posts: 19
Groups: None
Is there any function in P3e which automatically updates the progress of activities solely on where the data date is placed?

For example, if I were to drag the data date two weeks forward could P3e automatically start any activities that fell under that time period. And could it do this without extending any dates.

Cheers,

Matt Lovkis

Replies

ruben quintal
User offline. Last seen 16 years 41 weeks ago. Offline
Joined: 26 Sep 2006
Posts: 33
Groups: None
Mathew,

Run the "update progress" under tools menu, enter the desired date when prompted and then click run.
Hope this helps.

BEN
Rodel Marasigan
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Mathew,

I think you’re referring to Progress Spotlight where you can update your progress against you data date. Any activities highlighted by progress spotlight will be updated automatically without extending dates.

HTH
Rodel
Karim Mounir
User offline. Last seen 10 years 7 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Matthew,

U can use the "Schedule % complete" to show how much of the activity’s baseline duration has been completed so far (till the data date).

U can make a copy of the schedule that u work on and assign a baseline to it, then update the schedule as per ur data date and u’ll find the "Schedule % complete".

HTH.

Regards,
Karim