Hi,
When importing a project from P3 v3.1 to P3e v 4.1, how and what controls how v4.1 determines what type of resource it is.
I have imported a project, and some of the resources are now non-labour, and v4.1 will not allow me to change the resource type.
Any suggestions / advice.
Regards
Kevin