Drive Activity Dates by Default

2 replies [Last post]
Kaide Johar Manasi
User offline. Last seen 11 years 45 weeks ago. Offline
Joined: 16 May 2006
Posts: 16
Groups: None
I loaded my schedule with Budget Quantities and created histograms. The BQ spread linearly as expected since the ’Drive activity dates by default’ setting on resource assignment option was selected. But I want to add labor resource (other material resource also) and the budget quantities are not spreading over the duration of activity. I have checked on my other computer, it is working. I exported in xls and for the new resource the original duration for it is zero. What must go wrong? is it SDK or a bug in P6. Any help in this regard would be highly appreciated.

Replies

Kaide Johar Manasi
User offline. Last seen 11 years 45 weeks ago. Offline
Joined: 16 May 2006
Posts: 16
Groups: None
Thanks Arnold!
Default Unit/Time under Resource was zero. I changed it to 1 and now it is ok.
Arnold Puy
User offline. Last seen 9 years 37 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Kaide,

If I understood you correctly, go to project details --> calculations tab, try to play with "Reset Original Duration and Units to Remaining" or "Reset Remaining Duration and Units to Original". I am not sure, just try this.

Otherwise, try to check your Defaults Units/Time in Resources Window, it should not be blank or Zero. There should be a value (e.g. 8 or any value).

Regards,

Arnold