RE: Project Summarize

2 replies [Last post]
In P3e/c, projects are automatically summarised through the Enterprise Project Structure (EPS). If you require to view project data when the project is closed then you can summaries the data to pre-defined levels of the WBS. Go to the projects window and select the "settings" tab then select the level of WBS the data is to be summarised too. This allows users of Primavision to access summarised data in the Resource and Portfolio tabs.

Replies

Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
But for just reporting at a level 2 from a level 3 or level 4 plan, then this does what you need? Or what is the difference between what p3e/c does and the old summarise option in P3 (except the fact its 1000 times faster!)
Tony Banks
User offline. Last seen 20 years 34 weeks ago. Offline
Joined: 9 Dec 2002
Posts: 7
Groups: None
Data rolls up to Activity Code level automatically. You just need to open the projects then group by those activity / project codes.