Physicle Progress yet not taken in hand

1 reply [Last post]
shahzad kanwal
User offline. Last seen 13 years 37 weeks ago. Offline
Joined: 22 Feb 2011
Posts: 3
Groups: None

Hello to every one 

 

i need to show progress in bars activity which is not yed taken in hand but the time elapsed continutly 

for expample

 

Stone Pitching :     start Date :  01/11/2010   Finish Date:  08/06/2011

curent date is 22/02/2011 

but we yet not take this activity in hand so far so how can sohw in progress bar in diffrent Colur 

 

and also some others activities these kind of elapsed period so please tell me 

can it possibe that we show in progress bar 

 

i would be very thankful to all of you

 

Shahzad 

+923226617009

shahzad47@gmail.com

Replies

Fazeel Kamaran
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 21 Aug 2004
Posts: 18

SHAHZAD,

IF YOU HAVE NOT YET STARTED THE ACTIVITY, YOU CANNOT SHOW ITS PROGRESS ON THE CURRENT ACTIVITY BAR. BUT IF YOU ARE PRESENTING YOUR LAYOUT WITH TARGET / BASELINE COMPARISON THEN YOU CAN SHOW THE PROGRESS FOR THIS ACTIVITY ON THE TARGET / BASELINE BAR.

FOR THIS:

1 - ASSIGN TWO TARGET SCHEDULES TO THE CURRENT SCHEDULE

2 - TARGET 1 THE ORIGINAL BASELINE

3 - TARGET 2 UPDATE BASELINE WITH SAME DATA DATE AS THE CURRENT PROGRESS UPDATED SCHEDULE

4 - USING THE FORMAT COLUMNS OPTION YOU CAN DISPLAY THE REQUIRED INFORMATION:: ACT ID - DESCRIPTION - TAR1 ORG DUR - ORG DUR - REM DUR - ACT DUR - TAR2 % COMP - % COMP - TAR2 ES - TAR2 EF - ES - EF - TAR1 TOTAL FLOAT - TOTAL FLOAT - VAR TAR 1 EF

5 - GO TO "FORMAT - BARS" IN THE FORMAT WINDOW THAT OPENS CHECK VISIBLE FOR ONLY EARLY BAR REMOVE VISIBLE FOR OTHER BARS (OR DELETE THEM)

6 - FROM THE DROP DOWN ARROW SELECT TAR 2 AND ADD A BAR GIVE ITS POSITION AS 2 MAKE SURE THE "PROGRESS" BOX IS CHECKED / TICKED

CLOSE THE FORMAT BARS WINDOW.

THE CURRENT EARLY BARS AND THE TARGET BARS WILL BE VISIBLE IN THE BAR AREA. IF THE TARGET BARS ARE NOT VISIBLE, THE GO TO FORMAT - ROW HEIGHT AND INCREASE THE ROW HEIGHT FOR ALL BARS TILL YOU SEE THE TARGET BARS.

THE TARGET BARS WILL APPEAR BELOW THE CURRENT BARS. IN THE EXAMPLE YOU HAVE GIVEN, THE EARLY BAR OF THE ACTIVITY WILL BE SHIFTED TO 22/2/2011 OR ANY OTHER DATE LATER THAN THE DATA DATE (OR IN RELATION TO LINKS WITH PREDECESSORS). THE TARGET BAR FOR THIS ACTIVITY WILL BE BELOW THIS EARLY BAR AND WILL START FROM 1/11/2010 UPTO 08/06/2011 AND WIL HAVE PROGRESS SHOWING ON THE BAR. MAKE SURE TO FORMAT ALL TARGET BARS IN GREY COLOR SO THAT OTHERS WILL NOT CONFUSE WHAT THEY ARE. THE PROGRESS ON THE TARGET BARS WILL APPEAR IN BLUE.

I HOPE THIS ANSWERS UR QUESTION.