Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

TIME TAKEN FOR SCHEDULING

17 replies [Last post]
Kris Harry
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Hi friends,

I will like to know how long it typically takes a planner to develop a schedule of 500 and 1000 activities in P3 with cost and resources loaded.

I will also like to have views on if the planner should work independently or involve team members like project manager or others in the schedule preparation process.

Kris

Replies

Kris Harry
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Thanks Suresh,

Yes, before we lay hands on activities we need to be fully abreast of specifications and contract conditions which frequently give other requirements to be incorporated in the schedule.

Kris
Suresh Devarajan
User offline. Last seen 10 years 2 weeks ago. Offline
Joined: 11 Jul 2004
Posts: 24
Groups: None
Oh One Last Thing the key to a successful baseline schedule is Know your Specifications.....Know your Specifications....Know your Specifications coz when things go tough that is what we go after and not assumptions made. Moreover, specifications will indicate the windows of operation, shutdown period if any, testing process and quality control, submittals to be made and there approval durations, milestone and other criteria specially for the particular project. Therefore in one nut shell know your specs prior to start laying your hands on the activities and durations.
Suresh
Suresh Devarajan
User offline. Last seen 10 years 2 weeks ago. Offline
Joined: 11 Jul 2004
Posts: 24
Groups: None
Yeah I agree with Kris. Selling your schedule and getting the commitment of the Team members is very important coz as planners we can go through the sequence of work on a overall picture but to understand the scope of work in detail and the resource needed to build the work depends solely on the knowledge of the people who are going to build the work. so take all comments and review them coz each and everyone in the team who builds one part of the work knows only there part of the work but it is the scheduler who hears all the parts completes the puzzle. Additionally, How many times we would have heard the guys who build the work out there complain that the schedule is not realistic and when there point gets proven then the baseline schedule will be a mere wall paper attractive but not purposeful.
Adios Planners,
Suresh
Kris Harry
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Thanks Bill,

I agree - that’s what I keep doing - the only problem comes when some clients demand a detailed schedule in the beginning. We have to live with it.

Kris
Bill Guthrie
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
ok kRIS

Then suggest this is where you earn your pay, based on your knowledge and all informaiton available, build a high level schedule with lots of float and give client the key milestones only, and then you have to live with it. So then go to vendors and obtain info, by giving vendors your delivery milestones the project becomes schedule driven not cost driven.

good luck,bill
Sukumaran Subaram...
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Kris,

Believe the staffs are well experienced and knowledgeable. They must be able to guide you with their knowledge which they earned through their past working experiences, unless your company hire all the freshies to do the work.

If the engineers do not want to guide you, go ho ahead and develop the schedule based on your experience and once completed print it and discuss with them. Let them review the schedule, get the feedback and make a changes accordingly before submission.

Regards.
Kris Harry
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Dear Bill,

I agree that we do not wait for precise details of material deliveries or info from team members. We use our experience and best judgement. But problem comes when clients want a baseline schedule in 2-weeks after contract award and want to freeze it. It will then be used for progress comparison purposes during project execution.


Kris




Kris Harry
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Dear Bill,

I agree that we do not wait for precise details of material deliveries or info from team members. We use our experience and best judgement. But problem comes when clients want a baseline schedule in 2-weeks after contract award and want to freeze it. It will then be used for progress comparison purposes during project execution.


Kris




Bill Guthrie
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
Kris

You do not wait for detailed timeframes on materials, you go ahead and build the schedule identifying the known materials, and as the REQs return,then fine tune the durations accordingly.

Build it, then flesh it out then backwards pass it with updated info.

regards bill
Ganesan Sebrenmani
User offline. Last seen 11 years 25 weeks ago. Offline
Joined: 10 Nov 2003
Posts: 12
Groups: GPC Malaysia
Hi Guys,

For 1000 activities it may take more than 5-6 days depending on repetiveness of each activity. ( Ex : if you are repeating a set of 200 activities for 5 types of phases than it just a copy and paste method)
If it totally ONE whole 1000 activity project, you’ll need a month or so to get all the details and input them in schedule to retain the logic and practicality.

the site team shall have a lot of details of material deliveries and other infos. please refer to them.
Sometimes it’s up to the planner to schedule a activity’s duration based on his own judgement.

Hope that’s help

regards,
ganesan
Kris Harry
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Hi Guys,

Thanks for feedback. For an buildings project - not very complex - I think 5-6 days period may not be enough. Frequently it happens that all team members are not fully knowledgeable about details in the beginning of the project when baseline is being prepared. Material deliveries may not be known, subcontractors are not finalized.

Kris
Sukumaran Subaram...
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Hi,

As Bill and Shahzad mentioned. Let your team members involve in schedule development. Get their commitment and discuss on productivity rates to prepare a realistic workable schedule.

Let they understand the work sequences when you work on detail schedule. This will help the team members especially when you start to update the schedule.

Also it will make your life easy. Not to crack your head on your own and let the team members to feel the pressure too.

Remember the motto: TOGETHER WE EXCEL or TOGETHER WE FAIL.

Regards.
Shahzad Munawar
User offline. Last seen 9 years 30 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
Hi kris

Your schedule of 1000 activities with fully resource and cost loaded will take at least five to six days.

This will also depends upon nature of activities associated with the project

As regards cooperation of your team memebers, sure , without their involvement it is not possible to prepare, execute and monitor any schedule.
Shahzad Munawar
User offline. Last seen 9 years 30 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
Hi kris

Your schedule of 1000 activities with fully resource and cost loaded will take at least five to six days.

This also depends upon nature of activities associated with the project

As regards cooperation of your team memebers, sure , without their involvement it is not possible to prepare, excute and monitor any schedule.
Sunil Kumar
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 31 Mar 2005
Posts: 84
Groups: None
That a nice one Bill and I totally agree with you.

Sunil
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
I agree Bill’s word.
A "successful" schedule is not the effort of scheduler, it’s an effort of the whole team.
Bill Guthrie
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
Hi Kris

Your question will recive replies with lots of varables,its so broad.
Its in 2 parts.
1. Time to develop
Thats very hard to say, it depends on your experience, software used, and source data,printed or electric,etc.

2. 2nd part is easy, If you want to make a good schedule and retain your job, you had better involve all team members,and make it a OUR schedule not a MY schedule. Team member buy in is critical. Having said that, at what point you want Team buy in is up to you.
You might want to make a OUTLINE schedule, high level and let the team refine it.
The final product you will have to live with, and take advantage of everyones knowledge, get their buy ins or you will be spending more time defending your schedule then planning.
If they are involved from day one, they are champs of OUR schedule and will fight for it, not towards it.

Have fun
Regards bill