How to find out loops

3 replies [Last post]
Matthew Lin
User offline. Last seen 11 years 40 weeks ago. Offline
Joined: 20 Apr 2010
Posts: 20
Schedule run terminated as loop is detected. how can I know where is the loop?

Thanks.

Replies

harzelli bouasria
User offline. Last seen 4 years 50 weeks ago. Offline
Joined: 15 Oct 2008
Posts: 42
hi
simply you can click directly on the schedule icon in the toolbar (it’s like a watch, then select view on screen.

good luck
Matthew Lin
User offline. Last seen 11 years 40 weeks ago. Offline
Joined: 20 Apr 2010
Posts: 20
Thank you, Shareef! The problem is solved.

I always use F9...
Shareef Abdul Azeez
User offline. Last seen 3 years 14 weeks ago. Offline
Joined: 19 Sep 2005
Posts: 183
Hi

Go to tool -> Schedule and run

This will generate a schedule report which will give you all details of where the loop is.

Regards
Shareef