P3 changing dates

2 replies [Last post]
Mike Miller
User offline. Last seen 12 years 29 weeks ago. Offline
Joined: 6 May 2010
Posts: 20
Groups: None
See the pictures for reference.

before

after

Why is it changing the construction activities so they strart at the beggining when they are supposed to be succesors of "Construction"

Replies

Shah. HB
User offline. Last seen 1 year 9 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Mike

The way you run the schedule is quite incorrect

You use actual dates to the activities but the data date is not scheduled accordingly

Data date is the start date to run the scheduling algorithm
Rodel Marasigan
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Mike,
The problem is the predecessor because it was progress 100 percent complete sitting after the data date therfore the successor will run on the data date.

Note: All actual progress activities specially completed should sit after the data date and remaining will run after the data date.
Data Date mean Status date (cut-off of actual completed activities).