resource loading for late S curve

3 replies [Last post]
Caner Odabasi
User offline. Last seen 12 years 28 weeks ago. Offline
Joined: 19 Feb 2010
Posts: 5
Hi All
I want to make resource loading for manhours due to late S curve, but when I select late dates in selection criteria for tabular reports resource loading, I get loading for early dates again.
Is anyone have a solution for this problem?
Thanks

Replies

Shah. HB
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
You are welcome .I trust you got it
Caner Odabasi
User offline. Last seen 12 years 28 weeks ago. Offline
Joined: 19 Feb 2010
Posts: 5
Tnx much Shadul
Shah. HB
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi caner

In tabular reports select resource option in that choose tabular,select the resource you want to generate s curve early or late,In the time scale tab select late and provide none for early and target options.save it as you wish then run it. It will create a dbf file use the data generated to produce scurve