Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Generate S Curve after resource Loading in P3???

9 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear Sir,
If some body can help me by noting the point wise approach to generating a S Curve after resource loading i would be Grateful.
regards
deb

Replies

Mohd Anjum
User offline. Last seen 10 years 10 weeks ago. Offline
Joined: 12 Feb 2011
Posts: 21

Can any body tell how to load a resource and prepare resource loading schedule,

indirect labour schedule and direct labour schedule?

plz help me .if its long answer plz tell me the refrence.

Pranab Kumar Deb
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
thansk mr David it works perfectly well with google advanced search
regards
deb
David Moses
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 20 Oct 2004
Posts: 122
Hi There;

For search option in PP please check this:

http://www.planningplanet.com/forum/forum_post.asp?Cat=3&Top=22552.

I think it helps for the time being.

Regards
Pranab Kumar Deb
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
i fully agree with Bijaya , search option in planning planet will definitely help planners to have exactly the information that they are looking to else a lot of hard work by senior planners are wasted.
regards
deb
Pranab Kumar Deb
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
thanks mr.bijaya and mr.Akin Adurosakin for the help
regards
deb
Bijaya Bajracharya
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
I mean the SEARCH function should be functional.
Bijaya Bajracharya
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
It seems there is a need of SEARCH function in Planning Plannet.
Akin Adurosakin
User offline. Last seen 15 years 23 weeks ago. Offline
Joined: 29 Sep 2003
Posts: 16
Try the link below; the result could be helpfull.

http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=26460.


Regards,
Akin Adurosakin
Nigeria
Bijaya Bajracharya
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
If you have resource loaded your activities, you have done the most time consuming part. In fact the S curve is already there now - and what you need to how to view it.

Press the button "Resource/cost profile" which usually appear on to with bar chart icon on top. If you don’t see it, just go to View and then Ressource Profile.

You will see the profile at the bottom of the screen. Click "Display" button and then choose curve. If you also want histogram, choose that as well.

There are various filters and selection you can then apply depending on your need.

Good luck