Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Add resources using Global change, P6

2 replies [Last post]
abbas india
User offline. Last seen 13 years 45 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35
Hi,

Please let me know how to add resources to activities using global change in P6.

In P3 there was add resource option.

Replies

abbas india
User offline. Last seen 13 years 45 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35
Dear Arnold,

Thank you very much for your help.

Ok after assigning the resources as you know in P3 we can export it to Excel (dbf format etc...) and we can add the budgeted units corresponding to each resourse assignment and if we import it it will be reflected in P3.

Could you please help me again how the same can be done using P6.

Many thanks,
Abbas.
Arnold Puy
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147