Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to add Budgeted Units directly using Global change

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 40 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi

I want to add for all concreting activities same Budget units for eg 240.......using global change.....as we used to do in P3.1

So in if statement i selected activity name..Concreting.....

But when we come to then statement..in P6.1 , we have to add two parameters, how to use these parameters to add my budgeted units = 240 for all concreting activities.....

can anyone guide me..
regards,

Haresh Jayanth

Replies

Rodel Marasigan
User offline. Last seen 4 days 11 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
See sample below:
Global Change