starting remaining works program

2 replies [Last post]
Kumar I
User offline. Last seen 14 years 22 weeks ago. Offline
Joined: 15 Jul 2003
Posts: 52
Groups: None
while preparing a remaining works program,at the data date,many activities are progressing at the same and these activities will be with out predecessors like project commencement which has elapsed much earlier,which may lead to false schedule calculations,what is the remedy for this situation

Replies

Safak Vural
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 12 May 2008
Posts: 117
Dear Kumar,

If you are going to make a revision you can revise all relations and use Retained-Logic (Schedule Options) in order to show activities started but will continue later more realistic. On the other hand the most annoying part will be many started activities which will be and stacked up to the data date that will give you a resource histogram with mountain peaks after data date for 3-4 weeks (!). You can suspend the works which you will not be working until the planned date you will assign resources on site (From Dates Window in P3). This is a CLIENT-CONTRACTOR issue but try not the change the durations. Be careful when changing relations & Suspends that will change the critical path and check the situation in a detailed way in every progress update.

Regards,

Safak
Samer Zawaydeh
User offline. Last seen 5 years 39 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Kumar,

You can use a dummy activity and call it "start of remaining activities" and then link as usual from this point on.

Best,

Samer