How to Move Date Sight Line?

4 replies [Last post]
Sam Abbitt
User offline. Last seen 15 years 45 weeks ago. Offline
Joined: 14 Jan 2009
Posts: 6
Groups: None
We have a contract schedule that was issued in December. The dates cannot be altered. However, I want to print a copy of the December schedule, but with the Date Sight Line indicating today’s date. I can’t figure out how to move the line to today’s date without running the schedule and changing the early start/finish dates. Can someone please tell me how to do this? I am using Primavera P3. Thanks.

Replies

Sam Abbitt
User offline. Last seen 15 years 45 weeks ago. Offline
Joined: 14 Jan 2009
Posts: 6
Groups: None
Thanks everyone.
Sajid Balma
User offline. Last seen 13 years 22 weeks ago. Offline
Joined: 8 Jun 2007
Posts: 151
Groups: None
1. Click Data
2. Click Calendars...
3. Click Global Calendar
4. Click Standard...
5. Select a new date under Data Date
Close windows
Now your schedule has new sight line as per your new data date without any change in the schedule.

TAAAADAAAA
Sam Abbitt
User offline. Last seen 15 years 45 weeks ago. Offline
Joined: 14 Jan 2009
Posts: 6
Groups: None
Not sure why, but when I go to copy the schedule it keeps telling me "Invalid Project Name".

Any ideas?
Jean-Philippe Sam...
User offline. Last seen 3 years 44 weeks ago. Offline
Joined: 7 Feb 2007
Posts: 11
Hi Sam,

If it is only for printing, a turnaround for your problem may be:
(Make backups before !)
- Make a copy of your schedule,
- Set the copy as a target for your schedule.
- Update the data date of the current schedule
- In the bar chart, hide all the bars but the Target Bar.

Hope this helps