Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

histogram for actual and planned manpower in P3

4 replies [Last post]
Umer Mehmood
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 19 Jun 2008
Posts: 26
Dear All

I am unable to draw histogram that shows both actual and planned man power per week or per day (any time) todate .

thankyou for reading my question

Regards

Umer Mehmood
Planning Engineer

Replies

Umer Mehmood
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 19 Jun 2008
Posts: 26
I did not get the answer from any one
but
i thought of one answer

Primavera can give values of current project planned progress and other on target one ,if we make target plan in such a way that the oll ather things remain same expect planned resources than we can enter actual value in the target plan ,
Be carful in updating the target and donot update resources , this method can give
planned histogram
actual target histogram

Hope you have pick it

Regards

Umer
Ahmed Khan
User offline. Last seen 15 years 42 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Umar,

Did U get the solution for the above question..?

If yes plz forward me to onlyazeem4u@yahoo.co.in

Regards

Maask
Umer Mehmood
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 19 Jun 2008
Posts: 26
Thank for Reply

Actually i want the report on primavera outlook format,i can generate report in excel but it looks fabricated ,Primavera reports give look a system generated report and people believe that it has not been fabricated (although it can be fabricated even in oulook form)

thanks for replying
Mohammed Mujtaba
User offline. Last seen 11 years 3 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 23
Dear Umer,

You can get the planned manpower from resource loading. The actual manpower can be tracked daily based on site reports.