Global change

5 replies [Last post]
Alexandre Faulx-B...
User offline. Last seen 2 years 31 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355
Hello Planners,
I am going to use Global change to make tasks shorter by a) reducing the BQ, b)making the assigned resource "driving"
I have found the Resource Driving Flag (RDRV) argument in the Global Change list; but I cannot find how to use it: I have tried RDRV EQ "YES", "Y", "1", "T", with no success
Please help,
Alexandre

Replies

Joao Ribeiro
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
Glad to be of help.
Joao Ribeiro
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
Yes, I think the answer is:

then RES EQ(AD) XYZ
and RDRV EQ "*"

Using it to turn all selected resources into driving. Or, perhaps, using two steps:
- First, changing the resources
- Second ,converting then to driving.

It is also advisable to use "Trial Run" first, just in case...

Good luck

Bonne chance.
Joao Ribeiro
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
Use " " or "*" for non resource driving, resource driving with EQ or NE.

HTH