Hi Everybody ,
I am stuck up with a problem , and hope to find answers in this forum.
Background :- I have been asked to prepare level 4 execution programme for shutdown of a refinery , It should not have early start or early finsh dates , but only in terms of days such as D1, D2 etc and i have to provide allocated manhours against the activities.
I have absolutely no idea how i can avoid start and finsh dates in the coloumns and how i can show budgeted quantities against activites in a seperate coloumn.
Also i want your help in evaluating my understanding of level 4 programme.
01 :- Main refinery ( Name )
01.01 :- Units in refinery.
01.01.01 :- Different equipments in each units
01.01.01.01 :- Individual activities to be performed in each equipment.
Your help is urgently required and thanks in advance for the same.
regards,
Replies