First assign your target sch. (BASE) to the one ull be updating (PROG).
1- Open (PROG), click on "Tools" --> "Project Utilities" --> "Targets".
2- Select the (BASE) sch. from the drop menu - it must be located in the same folder as of your (PROG) sch.
3- Once selected (by pressing OK in the previous window), right click any where in the "Bar Chart" area, and click on "Bars".
4- In the window titled "Bars", click anywhere to add the Target bars (a window appears titled Add Bar Definition), type an appropiate desc. and choose the "Start point/End point" to read the "Target 1 early/late start/finish" by right clicking on the "Early start/finish" and selecting from the drop-down menu.
5- Set the size of bars and endpoints as u want.
6- In the "Add Bar Definition" window, set the position of the Target 1 bars to be #2 (located at top right).
7- Now the two bars should be appearing together in different positions (if the 2 bar sizes arent exceeding the row height).
Could be a few things, check first that your row height is large enough and where you have the PROG and BASE you have nominated to be in different positions.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks guys,
Setting up new bars did the trick. Thanks!
Mangesh,
It shows % remaining of what??
P3 has remaining duration and res/cost percent expended.
It will show you the percent complete and not the % of work remaining.
REMAINING DURATION will show you the no. of days left and not %, while res/cost percent expended will show you zero value, if its not cost loaded.
Hope, i got ur problem correctly
ANYWAY, HAPPY BIRTHDAY DEAR.
Thought u must have gone on vacation. Njoi
hi
i am trying to use the column % remaining, it should show the % remain of the activity, but it shows zero, why it is so.
cheers
mangesh
Also,
Add columns TARGET1 EARLY START and TARGET1 EARLY FINISH, to compare the Target V/s actual dates.
Add one more column of VARIANCE to check the difference in the dates.
Cheers,
Ravi
Hi Brian,
First assign your target sch. (BASE) to the one ull be updating (PROG).
1- Open (PROG), click on "Tools" --> "Project Utilities" --> "Targets".
2- Select the (BASE) sch. from the drop menu - it must be located in the same folder as of your (PROG) sch.
3- Once selected (by pressing OK in the previous window), right click any where in the "Bar Chart" area, and click on "Bars".
4- In the window titled "Bars", click anywhere to add the Target bars (a window appears titled Add Bar Definition), type an appropiate desc. and choose the "Start point/End point" to read the "Target 1 early/late start/finish" by right clicking on the "Early start/finish" and selecting from the drop-down menu.
5- Set the size of bars and endpoints as u want.
6- In the "Add Bar Definition" window, set the position of the Target 1 bars to be #2 (located at top right).
7- Now the two bars should be appearing together in different positions (if the 2 bar sizes arent exceeding the row height).
HTH.
Regards,
Karim
Hi Brian,
Could be a few things, check first that your row height is large enough and where you have the PROG and BASE you have nominated to be in different positions.
Cheers.
Karen