Compare with targets

6 replies [Last post]
Brian Chan
User offline. Last seen 16 years 48 weeks ago. Offline
Joined: 7 Oct 2007
Posts: 8
Groups: None
Hi,

I’m somewhat newer to P3. I’ve got a P3 schedule to manage and to progress, but I’d like to see the actual and projected against the planned bars.

I think I have my Target schedule set (BASE) and the one I will be progressing set (PROG). I still only see my PROG schedule.

What am I doing wrong?

Replies

Brian Chan
User offline. Last seen 16 years 48 weeks ago. Offline
Joined: 7 Oct 2007
Posts: 8
Groups: None
Thanks guys,

Setting up new bars did the trick. Thanks!
A D
User offline. Last seen 4 years 14 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Mangesh,

It shows % remaining of what??

P3 has remaining duration and res/cost percent expended.

It will show you the percent complete and not the % of work remaining.

REMAINING DURATION will show you the no. of days left and not %, while res/cost percent expended will show you zero value, if its not cost loaded.

Hope, i got ur problem correctly

ANYWAY, HAPPY BIRTHDAY DEAR.

Thought u must have gone on vacation. N’joi
Mangesh Khuspe
User offline. Last seen 1 year 18 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 162
hi
i am trying to use the column % remaining, it should show the % remain of the activity, but it shows zero, why it is so.
cheers

mangesh
A D
User offline. Last seen 4 years 14 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Also,

Add columns TARGET1 EARLY START and TARGET1 EARLY FINISH, to compare the Target V/s actual dates.

Add one more column of VARIANCE to check the difference in the dates.

Cheers,

Ravi
Karim Mounir
User offline. Last seen 10 years 27 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Brian,

First assign your target sch. (BASE) to the one u’ll be updating (PROG).
1- Open (PROG), click on "Tools" --> "Project Utilities" --> "Targets".
2- Select the (BASE) sch. from the drop menu - it must be located in the same folder as of your (PROG) sch.
3- Once selected (by pressing OK in the previous window), right click any where in the "Bar Chart" area, and click on "Bars".
4- In the window titled "Bars", click anywhere to add the Target bars (a window appears titled Add Bar Definition), type an appropiate desc. and choose the "Start point/End point" to read the "Target 1 early/late start/finish" by right clicking on the "Early start/finish" and selecting from the drop-down menu.
5- Set the size of bars and endpoints as u want.
6- In the "Add Bar Definition" window, set the position of the Target 1 bars to be #2 (located at top right).
7- Now the two bars should be appearing together in different positions (if the 2 bar sizes aren’t exceeding the row height).

HTH.

Regards,
Karim

Karen Smith
User offline. Last seen 15 years 34 weeks ago. Offline
Joined: 22 May 2007
Posts: 16
Groups: None
Hi Brian,
Could be a few things, check first that your row height is large enough and where you have the PROG and BASE you have nominated to be in different positions.

Cheers.
Karen