pls help me in cost loading

4 replies [Last post]
Sinan Fahmi
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 17 Dec 2006
Posts: 68
Groups: None
hi all
i assign bugdet cost for each activities in my project and after i run cost loading report i found defrent cost showing to me for example
i have a round 100 activites for concrete work and the summary bugdet cost for concrete work should be 8504750, but after running cost load the bugdet for this item showing 1035400. and other summary came less than budet...

please help me in this matter

Replies

Kamarul Bahrin H...
User offline. Last seen 48 weeks 1 day ago. Offline
Joined: 15 Aug 2005
Posts: 23
hi sinan

i think you batter check on cost. click f7 and check all your cost. resource, cost to complete, cost variance. i quess you miss overthere.
Sinan Fahmi
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 17 Dec 2006
Posts: 68
Groups: None
please can you explain more...
A D
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Anoon, thats d best solution.

BTW, check ur resources. Have u done any global change and put cost units into resources, which are used somewhere else....

Anoon Iimos
User offline. Last seen 2 years 41 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
do it in excel!