Filtering Negative lag

5 replies [Last post]
Rahmat Hidayat
User offline. Last seen 7 weeks 16 hours ago. Offline
Joined: 30 Jul 2002
Posts: 82
I’ve Boss more crazy now, he ask me to filter all activities with FS negative lag. How to do that best in P3 ? but pls don’t ask to do that manually ’coz I’ll be crazy also.

Thx in advance if u r genius.

Replies

Rahmat Hidayat
User offline. Last seen 7 weeks 16 hours ago. Offline
Joined: 30 Jul 2002
Posts: 82
Thanks DATTATREYA I get the point. I ’ll try to filter them in Excel and marry them using lookup function. U r right it must be easy to change any relationships there in Excel as we want. After that I’ll try to re-import.I believe u r one of P3 masters.

Hi ulysses, I’m Contractor and also Client of our Subcontractors. My friend make that (-) lags before he go, so risk on me now..lol. I’m sorry dude the original question is not clear for u. Enjoy in Qatar, I think it’s good and safe country like Japan.
ulysses garcia
User offline. Last seen 13 years 47 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar
Rahmat,

Are you contractor or client side, who make this lags?

Also, are you trying to change lag to + ?, you do not mentioned it in your 1st original question..

make it clear what do you want to do
DATTATREYA PADHARTHI
User offline. Last seen 6 years 3 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90
Hidayat,

pl export all the successor relationship in the export feature in either dbf or\excel. You will get a list of all activities with successor , lag duration & type of relation ship. You can filter all negative lags. As for other details like title & codes, export the normal activity content in a separate file & link/marry these two files & produce whatever report you boss wants. I have just re-checked the procedure & it works well.

Cheers
Dattatreya
Rahmat Hidayat
User offline. Last seen 7 weeks 16 hours ago. Offline
Joined: 30 Jul 2002
Posts: 82
Oh ulysses..it means thousands of lags like sands in the beach. U know after that I have to change those negative lags to ss&ff positive lags. I hope this problem not happen to u :[). Anyway thanks a lot for your input.

I love Qatar.
ulysses garcia
User offline. Last seen 13 years 47 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar
You can give a list of lag to your boss in other option, using report then tabular; this will give you list of lags.
maybe in some software you can filter lags, but in p3 in wont.