How can the delay (in days) shown in a schedule ?

3 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear all,
I wanted to know how the delay in current program Versus the baseline program in activities & WBS level(subtotal) be shown in a schedule.
regards
deb

Replies

Sitansh Desai
User offline. Last seen 8 years 2 days ago. Offline
Joined: 12 May 2003
Posts: 10
Groups: GPC Qatar
Hi Deb,

You can assign Project Must Finish by Date (same as contractual completion date Or Target Project completion date). For assigning this date, you have to open the project, go to File, Project Overview, Project Must Finish By.

After assigning the above date, schedule the project and then add a column of Total Float, this will help you to identify "Real Delayed Activities" as sometimes Early/Late variance may be -ve but still activity may have +ve total float meaning activity itself is delayed and delayed it’s successors but still it has not delayed entire project.

Hope this will help you.

Sitansh Desai
Pranab Kumar Deb
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Thanks ashraf that was a great help
regards
deb
Ashraf Jahangeer
User offline. Last seen 8 years 32 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Pranab,

In P3 you can see the target Early/Late Variance for start and finish of activity or summary.

Insert a column and get the desired variance you want.


Regards,


Ashraf