Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How long/day (like 12 hrs or 16 hrs/day) can workers work in Shutdown projects

14 replies [Last post]
Ahmed A.
User offline. Last seen 12 years 23 weeks ago. Offline
Joined: 29 Nov 2010
Posts: 8

 

Dear All,   We are preparing for one of our plants shutdown.In our last shutdown we had 2 shifts of 12 hrs each and the shutdown lasted for 12 days.The upcomming shutdown is a major one and is expected for 40 days.   we are now deciding for how long/day (like 12 hrs or 16 hrs/day) can workers work and how long/month a labour can continuous work (like 15 days continuous without a day-off). Are there any standards available?   There are many factors like weather, capability of sub-cons, nature of work etc which decide this working time frame.BUT, Is there any generally accepted BEST PRACTICES HANDBOOK FOR TURNAROUND PROJECTS available with YOU.   Thanks a lot in advance for your great support.   Ahmed

Replies

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

http://www.ac-lawyers.com/news/2008/03/14/impact-of-shift-work-on-labor-...

This  University of Wisconsin research seems to be in agreement with our experience. The positive effects of shift work on productivity makes it the preferable option in place of over-time or over-manning [Provide with more people than necessary]. These last two are usually of last resort, shift work is of second resort if impractical to go for a single shift. In our experience only a small percentage of shift work tend to increase productivity in agreement with the tables provided by this site. Still there are no golden rules, particular situations require particular solutions and it is fine with me to leave the other possibilities always open. 
Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757

... if there are not enough employees for the required production on short term jobs they cannot object to the temporary increase of manpower using external contractors as long as they are still employed doing what they usually do. ... Here the preferred way to expedite shutdown work is through the use of external contractors to supplement in-house crews. ...

Just to be clear, I was referring to contract personnel specifically with respect to my comment on attracting the best labor.  A large contractor may have 100 welders working for it, but maybe 10-20 are really top-notch, best in class welders in high demand for critical (not necessarily critical path, but critical importance - safety, etc.) jobs.  When presented with a choice of job assignments - one including overtime pay and one not, the best workers seek the best compensation for their time/effort.  A refinery in Texas City that tries to hire contractors for a turnaround where they will run 8 hour shifts is going to have a tough time attracting good people and keeping them motivated to work when there are numerous other opportunities in the area for contractors to work 10 or 12 hour shifts and earn more money.  YMMV.

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Rafael

Thanks for the sentiment - I got a tub of onions pickled in balsamic vinegar from my 46 year old son.

When do we get Grandfathers day?

Best regards

Mike Testro

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Mike,

Congratulations and happy fathers day.

Best regards,

Rafael

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi All

You can get an inspired crew to put in the utmost effort for more than is reasonably expected in order to complete a pre-determined task.

Team spirit - brotherhood - mustn't let the team down - we are the best - all combine to provide a determination to see it through.

However you can't expect this to happen every week in normal construction processes - however much you pay them.

BTW - This is my 3000 post - just wanted to share it with you.

Best regards

Mike Testro

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Sunil,

Your comments are appreciated. I perceive you like the debating of issues and listening others as dissenting opinion do matter on any brainstorming session. At times not always the "best solution" is what you initially thought, therefore in any analysis for your shutdown jobs also the idea of two ten hours shifts shall be on the table as well as any other reasonable option.

We usually go to the option of increasing work crews and have them work during daylight. In very limited occasions there is need for shift work, we never rule it out as another alternative.

It is not the same shutting down a single distillation tower than many. In the case of a single distillation tower it makes sense to work on shifts as there is a limit on how many people can work at the same time on a single tower but if the job consists of many such towers it might be better to increase the number of crews and work during daytime where you have daylight, when the hardware stores and material suppliers are working and there is clear responsibility on quality as not two different crews work on the same activity.

Even cultural issues shall be taken into account, if your people got to look to Mecca at certain time of the day let it be and set working time as not to interfere with this need.

Not all jobs are equal.

Best regards,
Rafael

Sunil Babu
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Rafael,

Very much informative data.Thank u

Regards

Sunil.

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Also, overtime rates are not necessarily equal to double the standard rate.

You are right, here it varies by industry and if union shop, by what has been agreed, always above the minimum required by law. Locally in the construction industry overtime rate is 2x and requiring work at meal time is equivalent to 3x because after six hours of continuous work without meal time break everything becomes at 2x rate. If you do not work at meal time you do not get paid but there are required breaks your employer cannot get away so if you are required to work at meal time you will be able to eat something during the intermediate breaks that are always to be paid by the employer.

        meal time    

EQUIVALENT

regular work hours

1111 1111 8 on such 8hr work day
as per our laws1111       1122 10 on such 8hr work day
equivalent to1111       3111 10 on such 8hr work day
therefore work at meal time has the effect as if 3x on an 8 hours work day

There are other considerations in certain trades:

  1. Guess a deep sea diver cannot work 10 continuous hours.
  2. Same goes in less degree to other trades like exterior cement plaster under our tropical sun, or even worst at night in the dark.
  3. Cement plaster of concrete ceilings have lower limits.
  4. Epoxy painting with respirators has also its practical limits.
  5. Some trades work by piecework, such as masonry.
  6. Others by fixed production per work shift, such as cement plaster.
  7. Long hours on some trades do not increase crew production. Take for example cement plaster, the crew can only mortar the surface area they can finish within a few hours, more than that will be impossible unless you make up a special crew with extra finisher with the result that productivity is reduced.
  8. Long hours can reduce quality and increase risk of errors and probability of accidents.
  9. When a contractor or owner get their employees easy access to overtime employees will get it on the spot and will slow down productivity when switched back to regular shifts. You might end up with higher than average productivity in the short run, during the shutdown but when finished, the effect will be lower productivity when overtime is reduced back, it is a two way street. I have my reserves on some of these studies as well as on the referenced article by InterPlan. I have issues with the idea everyone must be on overtime, that it is a shutdown does not means every activity is critical.
  10. ...

The rules about overtime cannot be generalized, shutdown projects are not the exception they still must cumply with our laws, labor rates and union agreements which are more strict than the average Continental US Labor laws, same as with OSHA we have our local version called PROSHA which cannot be less stringent than US federal laws. Only on selected industries the application of federal minimum wage have been granted a waiver but neither the construction industry or oil and gas are within these exceptions.

Not generalizing means two ten hours shifts with 2 hours in between are not to be ruled out, same as two eight hour shifts each with an allowance of 2 hours for some overtime work and then 2 extra hours to make up the 24 hours work period.

Our unions are jealous about their work, perhaps same as yours, but if there are not enough employees for the required production on short term jobs they cannot object to the temporary increase of manpower using external contractors as long as they are still employed doing what they usually do. Arbitration with the local labor department is very fair to all parties, we have some exceptions to the federal minimum wage but we have an overtime rate of two.

Here the preferred way to expedite shutdown work is through the use of external contractors to supplement in-house crews. We find it more cost efficient.

Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757

Rafael, oil refining (where my experience lies) is a different ball of wax from pharmaceuticals.  No refinery runs shutdowns/turnarounds 8 hours per shift (at least, here in the USA) if they want the best qualified workers available to take an interest in their turnaround.  We have had a client in Central America who ran three 8 hour shifts a day, but that was a state owned company and the market conditions there for labor was much different than what we typically see where there is more competition.

Also, overtime rates are not necessarily equal to double the standard rate.  In many cases, there is a time and half rate (which can actually be 1.3x or 1.4x, etc.) up to a certain threshold number of hours per week before double time rates apply.

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Bernard,

  • 8 hours = 8x1 ~ equivalent to 8 regular pay hours
  • 10 hours = 8x1+2x2 ~ equivalent to 12 regular pay hours

This represents an extra 50% labor cost per day so the extra 2 hours shall represent 50% production increase per day for it to break even and make economic sense. Of course I understand the increased production shall be spread along all day, still a 50% productivity increase to offset the cost is a lot. If the average productivity per hour remains the same then overtime makes no sense.

In the analysis direct costs as well as cost of time shall be considered together as it is not just about production but also the high cost of overtime versus savings in cost of time. Remember that only critical activities will have an effect in total job duration and therefore in job cost of time.

Still we plan for some overtime on selected activities and try to limit the overtime to within the 10 work hours per day with an hour of meal time in between. We use overtime on a very limited amount and this keeps some sense of urgency.

Sense of urgency and rhythm of the work are one of my favorite words. I believe the starting days of a job will establish the rhythm and better be good, from the beginning there must be a sense of urgency. If the party starts with a bolero it will end up boring, if starts with salsa dancing it will be fun.

http://www.youtube.com/watch?v=IF-K9U4TcKo&feature=related

I have seen this type of overtime assignment across the board on the pharmaceuticals, maybe not the most economical from the point of view of direct construction costs but very important when the cost of time is so big that the extra cost well justifies the time gained. These guys start a plant as soon as the drug is approved, if a mega drug, every day lost represents millions lost forever to the generic manufacturers that will start producing the equivalent as soon as patent expires.

Best regards,

Rafael

Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757

In our experience, 10 hours per shift (per day) seems to be the sweet spot balancing productivity and financial incentive for field hands.  With 8 hour shifts (no overtime), workers can either get the wrong message (management isn't in a hurry, so neither am I) or be motivated to slow the work down to stretch out the project (and finally earn some overtime).  12 hour shifts generally don't gain much more productivity over 10 hour shifts - especially if your local laws mandate a second meal time / extended break.  Fatigue tends to be exagerrated over the medium to long term with shifts greater than 10 hours.  We prefer to see 10 hour shifts for most work and 12 hour shifts - if necessary - only for critical path jobs where increased supervision is applied.  See also:

http://www.interplansystems.com/turnaround-project-planning-primer/productivity.html

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Here after five consecutive hours of work you must have a lunch break otherwise it is at 3x regular rate, after total of 8 hours per day it would be overtime at 2x regular, rate the same if over 40 hours per week, this in the construction industry as each industry might have slightly different rules. Here it is common to agree in writing, as allowed by law, for lunch time to be 1/2 hour insteadof one so a regular 8 hour shift last 8-1/2 clock hours. We even have laws that require a coffee break. In addition there are other restrictions regarding minimum rest time per any consecutive 24 hour period. 

If you require people to work more than 12 hours a day, 8 at regular pay plus 4 at double rate the productivity will go down very fast. Also in the middle of your third 16 hours day (16+16+8=40), after accumulating 40 hours on your regular work week all would be at 2x regular rate, asuming you can get away with the minimum rests time.

This if you can survive the unions getting into your company, the labor department (local and federal) and probably a strike at your job. Although most probably you wont be able to get any workers as they would rather work for other contractor, the fun of having the strike, some damage to your equipment and a punch in the face to your management will be missing.

Take a look at the following reference.

http://cmdept.unl.edu/drb/Reading/overtime2.htm

There you will find interesting curves regarding how productivity is affected by working long hours on consecutive days. Photobucket Photobucket  

Are there laws in your country that protect labor, laws against slavery?

Is it better than two shifts with 8h/day?

AMAR SOOGRIM
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 20 Dec 2011
Posts: 8
Groups: None

Generally i found that running 16hrs shift is more efficent. we tried it on shutdowns before.