Scheduling P3 and the activities stay where they are?!

6 replies [Last post]
Jason Boud
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 20 Mar 2006
Posts: 6
I’ve just pushed the f9 key, moved the data date out expecting the non progressed activities to move out to the new date and sit on the right of the blue line but they haven’t moved!

What am I doing wrong? There’s got to be a check box I’m missing somewhere....

Cheers

Jason

Replies

Eugene K
User offline. Last seen 13 years 6 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 47
Groups: GPC Malaysia
if not mistaken.. there is an option to "apply" the datadate from the master to all the subs, when u schedle from the master.

can someone confirm?

long time didnt use subproj....
Jason Boud
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 20 Mar 2006
Posts: 6
I’ve been a bit dim, we’ve got sub projects and I thought that by scheduling the overall project it would move the data dates for all the subs...

Having now scheduled the subs all is happy!
Anoon Iimos
User offline. Last seen 2 years 31 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
check activies with constraints
Jason Boud
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 20 Mar 2006
Posts: 6
Thanks for your responses chaps, tried and checked both but sadly no fix!

We’ve sent a prx to Primavera so we’ll see what they come back with...
Eugene K
User offline. Last seen 13 years 6 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 47
Groups: GPC Malaysia
possibly you are NOT viewing current bar (ES/EF)
but viewing baseline (T1ES/T1EF)?
Akin Adurosakin
User offline. Last seen 15 years 9 weeks ago. Offline
Joined: 29 Sep 2003
Posts: 16
It’s strange but one possible reason is the option that you choose to apply when scheduling activities.

Check this: instead of pressing F9 go to ’Tools’ --->> ’Schedule’ --->> ’Options’. Select the ’General’ tab under "When scheduling activities apply" select ’Progress Override’. Then schedule.

If you select ’Retained Logic’ it could create the kind of scenario that you presented.

When you choose Progress Override, P3 ignores the relationship (logic) and allow the activity to be rescheduled.

Please just check it out and let me have your feedback.


Akin Adurosakin
Nigeria