Generate Resource loading report in P6

2 replies [Last post]
Sinan Fahmi
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 17 Dec 2006
Posts: 68
Groups: None

Dear Planners,

  is it possible to generate Resource loading report in P6 as we did previously in P3 and transfer it excel?

Regards,

Replies

Sinan Fahmi
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 17 Dec 2006
Posts: 68
Groups: None

Thanks alot Hannes de Bruyne.......

Hannes de Bruyne
User offline. Last seen 2 years 7 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None

 yes - use report wizzard.

 

Subject Area „Activity Resource and Role Assignments“ select „Time Distributed Data"  select columns, fields etc. Finaly output in ASCII File delimited as in EXCEL