export&import exel to P3

2 replies [Last post]
Drajat Permana
User offline. Last seen 12 years 20 weeks ago. Offline
Joined: 13 Jul 2006
Posts: 3
Groups: None
I try to copy schedule from microsoft project to P3 by

using export/import.

but always failed.

please give me advise for this matter to me. step to step by using export and import tool P3

Replies

Paul Harris
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
There is a paper on my web site which explains this process.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Eva Martin
User offline. Last seen 16 years 36 weeks ago. Offline
Joined: 15 Feb 2007
Posts: 8
Groups: None
export and import process from MS Project to P3 has still some bugs, you will be surprised to see everything imported to P3 but when you time analyzed the programme some activites are not moving according to their logic or relationship.

It would save you time if ’copy and paste’ the activity ID, Description and Duration rather than retyping it manually onto P3. (and) The rest has to be rebuild on P3 (e.g. link and resources)