Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

how can i adjust project target duration?

3 replies [Last post]
ELSON JOHN SANTOS
User offline. Last seen 17 years 16 weeks ago. Offline
Joined: 26 Nov 2006
Posts: 3
Groups: GPC Qatar

Replies

Jason Smith
User offline. Last seen 14 years 1 week ago. Offline
Joined: 11 Dec 2006
Posts: 4
Groups: None
If you choose to use the update target feature I would save a back up first. Make sure that you choose only the items that you want to have updated on the target file. It is easy to update more than you wanted to if you are not careful.
Eric EVRARD
User offline. Last seen 7 years 3 days ago. Offline
Joined: 4 Dec 2006
Posts: 25
Groups: None
Hello,
A project target is only another project recorded in your P3 files and then shown on your layout when selected.
You need to open the project you use as a target, change whatever you want and it will appear with its modifications on the project you use.
Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
read the tutorial of how to create a schedule... that will help