Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

RESOURCES LEVELLING

7 replies [Last post]
Kris Harry
User offline. Last seen 13 years 26 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Hi Guys,

Can you guys help me out with resources levelling. If we have a contract finish date imposed how does levelling help. Can we go for resource smoothing alone.

Kris

Replies

Kris Harry
User offline. Last seen 13 years 26 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Thanks Jaime and Brij,

I’ll try both the options as suggested.But I am having problem with the steps somewhere. Can u guys detail me the steps with an example.

Kris
Brij Patwari
User offline. Last seen 18 years 3 weeks ago. Offline
Joined: 28 Aug 2004
Posts: 13
Groups: None
Hi Kris!!
This is my experience and understanding:-
In P3 - Version 3.0, if u have assigned Project Finish date constrain (Which u can’t move) than u can go for Backward levelling which will fix ur End date, will use available float. However, it will change ur LATE START date and not the EARLY START DATE.
If u dont want to change any of ur start/finish dates, u can go for smoothening and selectr levelling with Time constraint option. This will level resource only in the available float. BUT THIS WILL INCREASE UR NO. OF CRITICAL ACTIVITIES, OBVIOUSLY..

REGARDS,

BRIJ PATWARI
PROJECT CONTROL ENGINEER,
RELIANCE
Jaime Linchangco
User offline. Last seen 15 years 49 weeks ago. Offline
Joined: 16 Jul 2001
Posts: 29
Groups: None
Hi kris,

You could try levelling by assigning Priority code for each activities.

Define a new Activity Code, say "Priority Code". 1 for most Critical, 2 for Critical, 3, for less Critical and so on and then assign the appropriate priority code to each activities. Note that P3 levels the activity with the highest priority (the lowest number) before activities with lower priority.

In Levelling under Prioritization, use this priority code.

Hope this one work for your schedule.

Good luck

Jaime
Paul Harris
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
Kris

The help file explains clearly how it levels if you search on the topic “How P3 Levels resources” how this works.

There are three smoothing options: None, Non-time Constrained, and Time constrained. Time constrained option will not extend the activities beyond their late dates and therefore not increase the duration of the project.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Kris Harry
User offline. Last seen 13 years 26 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Paul,

Many thanks Paul. What are the steps for resources levelling and upon levelling does the schedule change automatically or it is to be saved as an option available. I tried but did’nt get the kind of result expected - perhaps I missed some step.

Kris
Ronald Winter
User offline. Last seen 3 years 50 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
It is a common misconception that P3 Smoothing will not delay the project. Smoothing (as implemented in P3) is simply the name given to the amount of increase that the leveling routines go through above the stated maximum. Good luck!
Paul Harris
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
Krsi

Levelling allows the option of leveling within float and you may increase the available resources and then level to optimize the number of resources required.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au