Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource leveling

3 replies [Last post]
Achim Kempf
User offline. Last seen 9 years 14 weeks ago. Offline
Joined: 24 Nov 2004
Posts: 4
During Precommissioning one team has to do loop checks in 20 commissioning systems, which are partly related to each other. The systems contain 1 up to 250 loops. The team is able to handle 40 loops a day. How can I manage P3 to calculate the early start of the loopchecking per systemn respec. the sequence of the systems to be checked?

Regards Achim

Replies

Philip Jonker
User offline. Last seen 16 years 11 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi achim,

Forgotten me
Achim Kempf
User offline. Last seen 9 years 14 weeks ago. Offline
Joined: 24 Nov 2004
Posts: 4
Thanks Jaco it worked. Regards from Munich Achim
Jaco Stadler
User offline. Last seen 18 years 18 weeks ago. Offline
Joined: 8 Sep 2004
Posts: 299
Groups: None
Hi Achim

I WOuld Suggest you go to the Following Method.

1) Open a P3 Schedule (in Hours)
2) Create the 20 Systems as Activity
3) Calcultate the activity Durations

Example assume System has 80 loops and you said 40 loops a Day (Assume 8 working hours) This mean activty duration is 16 hrs

Do the system Inter Logic

Assign a Resource "Loops" BQ (Number of loops / Systems)

Press level (Assign the resource Loops) Make Normal & Max lvl 5 (40 loops /8 Hours)